Short answer: Float is the time an activity can be delayed without causing a problem. Total float is how long an activity can be delayed without delaying the project finish date. Free float is how long an activity can be delayed without delaying the early start of the next activity. Float is also called slack.

What is float in project management?

Float is the spare time in a schedule. If an activity has three days of float, it can start or finish up to three days late and the plan still works.

You find float with the critical path method. First you work out the earliest dates for each activity. Then you work out the latest dates. The gap between them is the float.

The dates you need

  • Early start (ES): the earliest time an activity can start.
  • Early finish (EF): the earliest time it can finish. EF = ES + duration.
  • Late finish (LF): the latest time it can finish without delaying the project.
  • Late start (LS): the latest time it can start. LS = LF − duration.

Total float

Total float is the time an activity can be delayed without delaying the project finish date.

Total float = LS − ES, or Total float = LF − EF. Both give the same answer.

Activities with zero total float are on the critical path. Any delay to them delays the whole project.

Free float

Free float is the time an activity can be delayed without delaying the early start of the activity that follows it.

Free float = ES of the next activity − EF of this activity.

If several activities follow, use the one with the earliest early start.

Total float vs free float: the difference

Total float Free float
What it protects The project finish date The early start of the next activity
Formula LS − ES or LF − EF ES of next activity − EF of this activity
Who shares it All activities on the same path share it It belongs to one activity only
If you use it Later activities on the path lose float No other activity is affected

Free float can never be more than total float.

A worked example

A small project has five activities. Activity A comes first. After A, there are two paths: B goes straight to D, and C goes to E and then to D. The schedule starts at day 0.

Activity Duration (days) ES EF LS LF Total float Free float
A 3 0 3 0 3 0 0
B 4 3 7 3 7 0 0
C 2 3 5 4 6 1 0
E 1 5 6 6 7 1 1
D 2 7 9 7 9 0 0

  • The critical path is A, B, D. It takes 9 days and has zero float.
  • The path A, C, E, D takes 8 days, so it has 1 day of total float.
  • Activity C has 1 day of total float but no free float. If C finishes a day late, the project still ends on day 9, but E must start a day late.
  • Activity E has 1 day of total float and 1 day of free float. D cannot start before day 7, so E can slip a day without touching D.
  • C and E share the same single day. If C uses it, E has none left.

Can float be negative?

Yes. Negative float appears when a fixed date or other constraint asks for a finish that is earlier than the schedule logic allows. It tells you the plan cannot meet the date as it stands. You then need to shorten the schedule, for example by adding resources to critical activities or by doing some work in parallel.

Why float matters

  • It shows which activities need the closest watch. Zero float means no room for delay.
  • It shows where you can move people or equipment without harming the finish date.
  • It helps you answer the question: if this task is late, does the project finish late?
  • It gives early warning. When float on a path keeps shrinking, that path may become critical.

Tips for the PMP, CAPM and PMI-SP exams

  • Do the forward pass first to get ES and EF. Then do the backward pass to get LF and LS.
  • Some books start the schedule at day 1 and others at day 0. The float is the same either way.
  • The critical path is the longest path through the network. It sets the shortest possible project duration.
  • A project can have more than one critical path.
  • Total float belongs to a path. Free float belongs to an activity.

Our PMP certification training and CAPM certification training teach the critical path method with worked examples. If scheduling is your main job, look at the PMI-SP exam prep course.

Frequently asked questions

Is float the same as slack?

Yes. Float and slack mean the same thing.

Can free float be greater than total float?

No. Free float is always equal to or less than total float.

Which activities have zero float?

Activities on the critical path usually have zero total float.

What is the formula for total float?

Total float = late start − early start, or late finish − early finish.

What happens when an activity uses its float?

If it uses free float, nothing else changes. If it uses total float that is shared with other activities on the path, those activities have less float left.

  • Dr Faiz Rasool
    CEO and Founder at PM Training School (PMI Premier and SAFe Transformation Partner)

    Faiz runs PM Training School, a PMI's Premier Authorised Training Partner and SAFe Bronze transformation partner.

    Dr Faiz Rasool is a multi-award winning Agile and Business Transformation Consultant, Speaker, Trainer and Coach who finely combines on one hand an in-depth knowledge and grasp of Project/Programme/Portfolio Management and on the other hand, experience and expertise in Business Strategy, Business Analysis and Change Management. A rare mix of competencies that perfectly blend and are needed for driving corporate growth. Faiz have demonstrated a track record of driving growth, managing successful transformation projects, improving Business Process, and successfully creating solutions for complex business problems.
    Faiz brings a mix of best practice thinking, practical experience and working knowledge of the local operating environment to projects and consulting engagements.

    View all posts