Short answer: The cost performance index (CPI) shows how well a project uses its budget. The formula is CPI = EV / AC, which is earned value divided by actual cost. A CPI above 1.0 means the project is under budget. A CPI below 1.0 means it is over budget. A CPI of exactly 1.0 means it is on budget.

What is cost management in project management?

Cost management is how a project plans, estimates, budgets and controls its money. The goal is to finish the work within the approved budget.

The PMBOK Guide, Eighth Edition, covers this under the Finance performance domain. It has four processes:

  1. Plan Financial Management: decide how the project will manage its money.
  2. Estimate Costs: work out what the resources will cost.
  3. Develop Budget: add the estimates together to set the cost baseline.
  4. Monitor and Control Finances: track spending and manage changes to the budget.

CPI belongs to the last step. It is part of earned value management (EVM), which compares the work done with the money spent.

The four numbers you need first

  • Budget at completion (BAC): the total approved budget for the project.
  • Planned value (PV): the budgeted cost of the work that should be done by now.
  • Earned value (EV): the budgeted cost of the work that is actually done.
  • Actual cost (AC): the money actually spent on that work.

CPI and the other earned value formulas

Measure Formula How to read it
Cost variance (CV) EV − AC Positive is under budget. Negative is over budget.
Cost performance index (CPI) EV / AC Above 1.0 is under budget. Below 1.0 is over budget.
Schedule variance (SV) EV − PV Positive is ahead of schedule. Negative is behind.
Schedule performance index (SPI) EV / PV Above 1.0 is ahead of schedule. Below 1.0 is behind.
Estimate at completion (EAC) BAC / CPI The expected total cost if the current cost performance continues.
Estimate to complete (ETC) EAC − AC The money still needed to finish the work.
Variance at completion (VAC) BAC − EAC Positive is under budget at the end. Negative is over budget.
To-complete performance index (TCPI) (BAC − EV) / (BAC − AC) The cost efficiency needed on the remaining work to finish on budget.

A worked example

A project has a budget of $100,000. By today, half of the work should be done. Only 40% is done, and the team has spent $50,000.

  • BAC = $100,000
  • PV = 50% of $100,000 = $50,000
  • EV = 40% of $100,000 = $40,000
  • AC = $50,000

Now apply the formulas:

  • CV = 40,000 − 50,000 = −$10,000. The project is over budget.
  • CPI = 40,000 / 50,000 = 0.80. Each dollar spent delivers 80 cents of work.
  • SV = 40,000 − 50,000 = −$10,000. The project is behind schedule.
  • SPI = 40,000 / 50,000 = 0.80. The team works at 80% of the planned rate.
  • EAC = 100,000 / 0.80 = $125,000. This is the likely final cost.
  • ETC = 125,000 − 50,000 = $75,000. This is the money still needed.
  • VAC = 100,000 − 125,000 = −$25,000. The project will end $25,000 over budget.
  • TCPI = (100,000 − 40,000) / (100,000 − 50,000) = 1.20. The team must earn $1.20 of work for each remaining dollar to finish on budget.

How to use CPI on a real project

  • Check CPI at regular points, such as every month or every sprint.
  • Read CPI and SPI together. A project can be under budget only because it is behind schedule.
  • Look at the trend. One low reading is a warning. Three in a row is a pattern.
  • Find the cause before you act. Common causes are poor estimates, scope changes and rework.
  • Update the forecast (EAC) and tell stakeholders early.

Common mistakes with CPI

  • Mixing up EV and AC. Earned value is the budgeted worth of the work done. Actual cost is what you paid.
  • Using money spent as a measure of progress. Spending half the budget does not mean half the work is done.
  • Putting the formula upside down. Earned value always comes first: EV / AC and EV / PV.
  • Ignoring a TCPI well above 1.0. It often means the original budget is no longer realistic.

CPI in the PMP and CAPM exams

Earned value questions appear in PMI exams. You may need to calculate a value or explain what a result means. Practise both. Our PMP certification training and CAPM certification training cover earned value step by step, and the PMP exam simulator gives you exam-style practice questions.

Frequently asked questions

What is a good CPI?

A CPI of 1.0 or more is good. It means the work costs what you planned, or less.

What does a CPI of 0.8 mean?

It means the project earns 80 cents of work for every dollar it spends. The project is over budget.

What is the difference between CPI and SPI?

CPI measures cost efficiency. SPI measures schedule efficiency. CPI compares earned value with actual cost. SPI compares earned value with planned value.

What is TCPI?

The to-complete performance index is the cost efficiency the team must reach on the remaining work to meet the budget.

Is cost variance the same as CPI?

No. Cost variance is a dollar amount (EV − AC). CPI is a ratio (EV / AC). Both use the same two numbers.

  • Dr Faiz Rasool
    CEO and Founder at PM Training School (PMI Premier and SAFe Transformation Partner)

    Faiz runs PM Training School, a PMI's Premier Authorised Training Partner and SAFe Bronze transformation partner.

    Dr Faiz Rasool is a multi-award winning Agile and Business Transformation Consultant, Speaker, Trainer and Coach who finely combines on one hand an in-depth knowledge and grasp of Project/Programme/Portfolio Management and on the other hand, experience and expertise in Business Strategy, Business Analysis and Change Management. A rare mix of competencies that perfectly blend and are needed for driving corporate growth. Faiz have demonstrated a track record of driving growth, managing successful transformation projects, improving Business Process, and successfully creating solutions for complex business problems.
    Faiz brings a mix of best practice thinking, practical experience and working knowledge of the local operating environment to projects and consulting engagements.

    View all posts