Short answer: A responsibility assignment matrix (RAM) is a grid that shows who does what on a project. The work is listed down one side and the people or teams are listed along the other. The best-known type is the RACI chart, which marks each person as Responsible, Accountable, Consulted or Informed for each piece of work. Some people call it a RAM matrix.
Table of Contents
What is a responsibility assignment matrix?
A responsibility assignment matrix links the work of a project to the people who do it. Each row is a task, activity or work package. Each column is a person, role or team. Each cell shows that person's part in that work.
The matrix answers three questions quickly:
- Who does this work?
- Who makes the final decision?
- Who needs to give input or be kept up to date?
The PMBOK Guide, Eighth Edition, lists the responsibility assignment matrix as a project management tool and gives the RACI matrix as one example. It notes that a RACI matrix is useful when the team includes both internal and external people.
What does RACI stand for?
- Responsible (R): the person who does the work.
- Accountable (A): the person who owns the result and signs it off. There should be only one for each task.
- Consulted (C): people who give input before or during the work. Communication goes both ways.
- Informed (I): people who are told about progress or results. Communication goes one way.
RACI chart example
Here is a simple RACI chart for a small software project.
| Activity | Sponsor | Project manager | Business analyst | Developer |
|---|---|---|---|---|
| Approve the project charter | A | R | C | I |
| Gather requirements | I | A | R | C |
| Build the solution | I | A | C | R |
| Test the solution | I | A | R | C |
| Accept the final product | A | R | C | I |
Read across a row to see everyone involved in one activity. Read down a column to see one person's full workload.
How to create a responsibility assignment matrix
- List the work. Use the work packages from your work breakdown structure (WBS) or your main activities.
- List the people, roles or teams across the top.
- Fill in each cell with R, A, C or I. Leave a cell empty if the person has no part in that work.
- Check each row. It needs one Accountable and at least one Responsible.
- Check each column. Too many R marks may mean one person is overloaded.
- Review the matrix with the team and agree on it.
- Update it when people or scope change.
Rules for a good RACI chart
- Give each task only one Accountable person. Two owners often means no owner.
- Give every task at least one Responsible person.
- Keep the Consulted list short. Every extra name slows the decision.
- Use roles, not only names, so the chart still works when people change.
- Keep the chart to one page where you can. Use a high-level chart for the whole project and detailed charts for each team.
RAM, RACI and other charts
- RAM and RACI: RAM is the general tool. RACI is one format of it. All RACI charts are RAMs, but a RAM can use other codes, such as "lead" and "support".
- RASCI: this adds an S for Support, for people who help the Responsible person.
- Organisation chart: this shows reporting lines. It does not show who does each piece of work.
- Work breakdown structure: this shows the work. The RAM connects that work to people.
Why project managers use a RAM
- Everyone knows their role, so less work is missed or done twice.
- Decisions are faster because the decision maker is clear.
- New team members can see quickly who to ask.
- Stakeholders know when they will be consulted and when they will only be informed.
The RAM in the PMP exam
PMI exams can ask what a responsibility assignment matrix shows, or which tool makes roles and responsibilities clear. Remember the key idea: one Accountable person for each task. Our PMP certification training covers this and other resource management tools. You can also read our guide to the principles of resource management.
Frequently asked questions
Is a RAM the same as a RACI chart?
Not exactly. A RACI chart is the most common type of responsibility assignment matrix. A RAM can also use other labels.
What is the difference between Responsible and Accountable?
The Responsible person does the work. The Accountable person owns the result and approves it. One person can hold both roles on a small task.
Can two people be Accountable for the same task?
It is best to have only one. A single owner makes decisions clear.
What is a RAM matrix?
It is another name people use for the responsibility assignment matrix. The M in RAM already stands for matrix.
When should I create the RAM?
Create it during planning, once you know the main work and the team. Then keep it up to date during the project.